2025-2026 Local Maintenance & Improvement Grant (LMIG) Projects

The City of Decatur is beginning a series of street resurfacing projects funded through the Georgia Department of Transportation’s Local Maintenance & Improvement Grant (LMIG). These improvements help extend the life of our streets and enhance safety for drivers, pedestrians, and cyclists.

The projects will include comprehensive maintenance along 1.68 miles of corridor segments, focusing on infrastructure for all users—motorists, pedestrians, and cyclists. Work will consist of:

  • Sidewalk and apron repairs where concrete is cracked, dislodged, or missing

  • Upgraded ADA-compliant curb ramps at intersections

  • Crosswalk restriping for better visibility and accessibility

  • Replacement of faded thermoplastic striping and regulatory signage

  • Base patching and full resurfacing of asphalt travel lanes

  • Roadway milling to preserve curb height and improve stormwater drainage

These improvements are designed to provide a longer-lasting, safer, and more accessible transportation network.

This page will be updated in real time as each project begins and progresses. Residents can check back regularly for start dates, updated timelines, and detailed impacts on traffic and parking.

For questions, contact Julie Harlan at julie.harlan [at] decaturga.com (404-987-7572) or Daniel McIntosh at dmcintosh [at] magnumpaving.com (404-538-0492).

Current & Upcoming Projects

 

Hillcrest Drive 

Start Date: March 17, 2026 (weather permitting)
Status: In Progress
Scope: Paving and roadway improvements

What to expect:

  • Construction activity and equipment along Hillcrest Drive
  • Temporary traffic changes and potential brief delays
  • Trash and recycling collection will remain on schedule
  • Emergency access will be maintained
  • Residents are encouraged to use caution when traveling through the area and watch for crews working in the roadway

Willow Lane

Start Date: Week of March 16, 2026 (weather permitting)
Status: In Progress
Scope: Installation of three new speed tables

What to expect:

  • Construction activity along Willow Lane during installation
  • Partial lane access at times; brief delays are possible
  • Trash and recycling collection will remain on schedule
  • Emergency access will be maintained
  • Residents are encouraged to use caution when traveling through the area and watch for crews working in the roadway

East Lake Drive

Location: Fayetteville Road to City Limits (current work between Upland Road and Pharr Road)
Status: Complete

Current Work: Crews will return to East Lake Drive this week to address concerns about pooling water near the intersection of East Lake Drive and Spring Street.

  • Concrete work is scheduled for Wednesday, October 22.

  • Milling and repaving will follow on Friday, October 24.

  • Repaving will be limited to the northbound travel lane between 1018 East Lake Drive and 928 East Lake Drive.

During this time, East Lake Drive and Spring Street will be closed to through traffic between Upland Road and Pharr Road. Drivers traveling through the area should follow posted detour signs.

Traffic, Parking & Access Impacts:

  • Temporary lane closures and detours during paving and concrete work

  • No on-street parking allowed while work is underway

  • Driveway access, trash collection, and emergency access will be maintained

Residents should expect construction activity, equipment, and temporary traffic changes. Please use caution when traveling through the area.


Church Street

Location: E. Ponce de Leon Ave. to E. Trinity Place
Start Date: August 25, 2025
Estimated Duration: Approximately 1–2 weeks (weather permitting)
Status: Paving complete. Final striping in progress. Additional work scheduled.

Upcoming Work:

  • A raised crosswalk installation is scheduled for Tuesday, Sept. 16 and Wednesday, Sept. 17 on a portion of Church Street.

  • During this work, Church Street will stay open, but drivers will need to enter from Sycamore Street or East Ponce de Leon Avenue. The road will be closed to through traffic between Sycamore Street and East Trinity Place.

  • The street will reopen to through traffic on Thursday, Sept. 18.

  • All businesses, driveways, and the surface parking lot off Church Street will remain accessible.

What to Expect:

  • Work hours: 7:00 a.m. to 6:00 p.m., Monday–Friday

  • Daytime noise from construction equipment

  • Traffic delays near the crosswalk installation area

  • Trash and recycling pickup will continue on schedule

  • Driveway and business access maintained


Feld Avenue

Location: W. College Avenue to Leyden Street
Start Date: Sept. 2, 2025
Estimated Duration: Approximately 3 days (weather permitting)
Status: Complete

Upcoming Work:

  • On Thursday, Sept. 19, the intersection of Feld Avenue and Leyden Street will be closed for follow-up work.

What to Expect:

  • Work hours: 7:00 a.m. to 6:00 p.m., Monday–Friday

  • Daytime noise from construction equipment

  • On-street parking restricted during work

  • Sidewalks will remain open, though minor disruptions may occur

  • Trash and emergency access will be preserved


Emerson Avenue

Location: Adair Street to Drexel Avenue
Start Date: Sept. 8, 2025 
Estimated Duration: Approximately 3 days (weather permitting)
Status: Complete

What to Expect:

  • Work hours: 7:00 a.m. to 6:00 p.m., Monday–Friday

  • Lane shifts and potential one-way traffic control

  • No on-street parking during work

  • Driveway access will be maintained

  • Trash and recycling pickup will continue as normal


East Davis Street

Location: S. McDonough Street to S. Candler Street
Start Date: August 27, 2025
Estimated Duration: Approximately 1 week (weather permitting)
Status: Complete

Schedule & Work Details:

  • Work hours: 7:00 a.m. to 6:00 p.m., Monday–Friday

  • Milling and paving followed by permanent striping

Traffic, Parking & Access Impacts:

  • Rolling lane closures during daytime hours

  • Road will remain open where possible, but alternate routes are recommended

  • On-street parking prohibited for the duration of work

  • Flaggers will assist with traffic control

  • Driveway access will be maintained where possible

  • Trash and recycling collection will remain on schedule