Oakhurst Streetscape Improvements
 |
|
(Click to enlarge) |
Budget: $1,507,000 Status: Under design Bid Date: November, 2008 Construction: January, 2009–October, 2009
Concept plan presentation-August 16 Master plan approved-September 17 Under review by GDOT
|
 |